The city of Ghent has welcomed a brand-new Krommewal Bridge over the Leie River, marking a significant upgrade for local infrastructure. This impressive installation, completed on 2025-05-10 20:30:00, promises to improve traffic flow and pedestrian access in the area.
- Nieuwe Krommewalbrug over Leie geplaatst zaterdag
- Brugdelen wegen 40 en 48 ton elk
- Logistiek omvat tramleidingen en kabels verwijderen
- Hijskraan plaatste brugdelen ondanks windaanpassing
- Auto’s mogen brug pas eind juni gebruiken
- Nieuwe brug steviger dan oude uit jaren 1990
Transporting the two massive parts of the bridge, weighing 40 and 48 tons respectively, was a logistical feat. The journey from Handelsdok to Sluizeken involved tram overhead wire removals, temporary telecommunication cable cuts, and road closures, capturing the attention of many local onlookers.
What makes this bridge replacement so important for Ghent’s infrastructure? How will it affect daily commuters and residents? Let’s explore the key points behind this engineering achievement.
This project raises some interesting questions about urban development and safety priorities. Why was the old bridge no longer sufficient? What challenges did the installation face?
- The former Krommewal Bridge, built in the 1990s, was too light for current traffic demands.
- The new steel bridge is sturdier, with one fixed and one movable section to accommodate river traffic.
- Strong winds required adjustments during installation, highlighting safety as a top priority.
- Police oversight ensured public safety during the complex transport and placement operation.
Looking ahead, residents can anticipate smoother transit and renewed pedestrian access soon. Will this new bridge become a symbol of Ghent’s evolving cityscape? Only time will tell, but for now, the focus remains on completing the final touches and welcoming the public back safely.