Final Stretch of Trans Java Toll Road Accelerates: Unveiling Impressive Progress Updates

"Trans Java Toll Road: Rapid Progress Updates"

The Probolinggo-Banyuwangi toll road, part of Trans Jawa, is under construction, with completion expected after 2025, involving significant investment.
Siti Rahmawati26 January 2025Last Update :
Pembangunan Ruas Terakhir Tol Trans Jawa Dikebut, Begini Progresnya
finance.detik.com

The construction of the Trans Java Toll Road is progressing rapidly, with the Probolinggo-Banyuwangi segment being a key focus. As of January 26, 2025, this 176.40 km stretch is crucial for connecting Merak to Banyuwangi, enhancing travel and trade across Java. Are you curious about the latest updates on this national project?

6 Key Takeaways
  • Trans Jawa Toll Road is incomplete.
  • Probolinggo-Banyuwangi toll spans 176.40 km.
  • Construction divided into two phases.
  • Phase 1 progress at 15.01% completion.
  • Phase 2 construction starts post-2025.
  • Total investment approximately Rp 23.39 trillion.
Fast Answer: The Probolinggo-Banyuwangi toll road, part of the Trans Java network, is currently under construction. This segment is vital for improving connectivity in Indonesia, with significant progress reported in various sections. Completion is expected in stages, with the first phase targeted for 2025.

Key Updates on the Probolinggo-Banyuwangi Toll Road Construction Progress

How is the construction of the Probolinggo-Banyuwangi toll road shaping up? This project is not just about building roads; it’s about boosting the economy and making travel easier for everyone. The ongoing work is divided into two phases, with the first phase already underway.

Info! This project is significant for Indonesia’s infrastructure development, impacting trade and travel. The U.S. has a keen interest in international infrastructure projects, as they can influence global trade dynamics.

Understanding the Phases of the Probolinggo-Banyuwangi Toll Road

The toll road is divided into two main phases. The first phase, from Gending to Banyuwangi, covers 49.7 km and is currently in progress. The second phase, which extends from Besuki to Banyuwangi, is yet to start. Here’s a breakdown of the phases:

Phase One: Current Progress and Timeline

The first phase includes several sections with varying progress levels:

  • Seksi 1 (Gending-Kraksaan): 100% land acquisition, 15.01% construction.
  • Seksi 2 (Kraksaan-Paiton): 97.4% land acquisition, 69.6% construction.
  • Seksi 3 (Paiton-Besuki): Two packages, with the first at 100% land acquisition and 56.1% construction.

Phase Two: Future Developments and Expectations

The second phase, which spans 126.72 km, is crucial for completing the toll road. It includes several sections, such as:

  • Seksi 4 (Besuki-Situbondo): 43.30 km.
  • Seksi 5 (Situbondo-Asembagus): 16.76 km.
  • Seksi 6 (Asembagus-Bajulmati): 37.45 km.
  • Seksi 7 (Bajulmati-Banyuwangi/Ketapang): 29.21 km.

In conclusion, the Probolinggo-Banyuwangi toll road is a vital project for Indonesia, enhancing connectivity and economic growth. As construction progresses, it will play a significant role in the future of travel and trade across Java.

Leave a Comment

Your email address will not be published. Required fields are marked *


We use cookies to personalize content and ads , to provide social media features and to analyze our traffic...Learn More

Accept
Follow us on Telegram Follow us on Twitter